CivilAxisCivilAxis
☕ Support🌐 Community

HE 600 A vs IPE V 600

HE 600 A is an HE section from the European (Continental) range; IPE V 600 is the closest equivalent in the European (Continental) range. They are close to interchangeable in bending: 5350 cm³ against 5320 cm³ of plastic modulus, a difference of 0.6%. HE 600 A is the lighter of the two at 178 kg/m against 184 kg/m, a saving of 3.3% on steel weight. IPE V 600 is deeper, 618 mm against 590 mm, which matters where the floor zone is tight.

Section properties side by side. Bold marks the more favourable value where one is.
PropertyHE 600 A
HE
IPE V 600
IPE
Difference
Mass178 kg/m184 kg/m-3.3%
Depth590 mm618 mm-4.5%
Width300 mm228 mm+31.6%
Web thickness13 mm18 mm-27.8%
Flange thickness25 mm28 mm-10.7%
Area226 cm²234 cm²-3.4%
Second moment, major (Iy)141,000 cm⁴142,000 cm⁴-0.7%
Plastic modulus, major (Wpl,y)5,350 cm³5,320 cm³+0.6%
Elastic modulus, major (Wel,y)4,790 cm³4,580 cm³+4.6%
Second moment, minor (Iz)11,300 cm⁴5,570 cm⁴+102.9%
Plastic modulus, minor (Wpl,z)1,160 cm³780 cm³+48.7%
Radius of gyration, minor (iz)7.05 cm4.88 cm+44.5%
Torsion constant (It)407 cm⁴506 cm⁴-19.6%

HE 600 A to EN 10365 · Continental Steel; IPE V 600 to EN 10365 · Continental Steel. Difference is expressed relative to IPE V 600.

How to choose between them

On stiffness, IPE V 600 has the larger second moment of area: 142,000 cm⁴ against 141,000 cm⁴, a difference of 0.7%. This matters more often than the strength comparison, because on normal floor spans deflection rather than bending capacity sets the beam size - so if the two are close on modulus but apart on inertia, the stiffer one is usually the better answer even when it is not the stronger one.

Measured as bending capacity per kilogram of steel, HE 600 A is the more efficient section: 30.1 against 28.9 cm³ per kg/m, 4.0% better. Over a floor of repeated beams that difference is real tonnage, though it is often outweighed by whichever section the fabricator can actually source.

The two diverge much more about the minor axis: HE 600 A has 1160 cm³ of minor-axis plastic modulus against 780 cm³, 48.7% more. If the member sees any minor-axis bending, or if it is unrestrained over a long length and lateral-torsional buckling governs, that gap decides the comparison even though the major-axis numbers looked equivalent.

In short, HE 600 A is the stronger section and HE 600 A is the lighter one; where those are the same section, it is the clear choice, and where they are not, decide on whether your design is governed by capacity or by tonnage.

Common questions

They are effectively equal in bending. HE 600 A has a plastic modulus of 5350 cm³ and IPE V 600 has 5320 cm³, a difference of only 0.6% - within the margin that section choice normally turns on. Compare stiffness and availability instead.

HE 600 A at 178 kg/m, against 184 kg/m for the other - a saving of 3.3%. Over a repeated floor beam that is a real cost difference, but check it against the deflection case before taking it.

Structurally it is the closest equivalent we hold: IPE V 600 gives 5320 cm³ of plastic modulus and 142,000 cm⁴ of inertia against 5350 cm³ and 141,000 cm⁴. Re-check deflection and the connection details before swapping, since the flange and web thicknesses differ.

IPE V 600, with a second moment of area of 142,000 cm⁴ against 141,000 cm⁴ (0.7% more). Deflection under a uniform load goes as 5wL⁴/384EI, so it is inversely proportional to I - on a span where the deflection limit governs rather than strength, this is the number that decides the section.

Related comparisons

UB 610×305×179 vs IPE V 600W 24X117 vs IPE V 600W 24X117 vs HE 600 AHE 600 A vs H-600x300x14x23-175
Rate this
No ratings yet
Sign in to join the discussion.