UB 762×267×173 vs W 30X116
UB 762×267×173 is an UB section from the UK Blue Book (SCI P363); W 30X116 is the closest equivalent in the American AISC Shapes Database. They are close to interchangeable in bending: 6200 cm³ against 6194.3 cm³ of plastic modulus, a difference of 0.1%. They weigh essentially the same, 173 kg/m and 172.6 kg/m. Both are about 762 mm deep, so either fits the same construction zone.
| Property | UB 762×267×173 UB | W 30X116 W | Difference |
|---|---|---|---|
| Mass | 173 kg/m | 172.6 kg/m | +0.2% |
| Depth | 762.2 mm | 762 mm | same |
| Width | 266.7 mm | 266.7 mm | same |
| Web thickness | 14.3 mm | 14.4 mm | -0.7% |
| Flange thickness | 21.6 mm | 21.6 mm | same |
| Area | 220 cm² | 220.6 cm² | -0.3% |
| Second moment, major (Iy) | 205,000 cm⁴ | 205,202 cm⁴ | -0.1% |
| Plastic modulus, major (Wpl,y) | 6,200 cm³ | 6,194.3 cm³ | +0.1% |
| Elastic modulus, major (Wel,y) | 5,390 cm³ | 5,391.3 cm³ | same |
| Second moment, minor (Iz) | 6,850 cm⁴ | 6,826 cm⁴ | +0.4% |
| Plastic modulus, minor (Wpl,z) | 807 cm³ | 806.24 cm³ | +0.1% |
| Radius of gyration, minor (iz) | 5.58 cm | 5.56 cm | +0.4% |
| Torsion constant (It) | 267 cm⁴ | 267.6 cm⁴ | -0.2% |
UB 762×267×173 to BS EN 10365:2017; W 30X116 to AISC Shapes Database v16.0. Difference is expressed relative to W 30X116.
How to choose between them
On stiffness, W 30X116 has the larger second moment of area: 205,202 cm⁴ against 205,000 cm⁴, a difference of 0.1%. This matters more often than the strength comparison, because on normal floor spans deflection rather than bending capacity sets the beam size - so if the two are close on modulus but apart on inertia, the stiffer one is usually the better answer even when it is not the stronger one.
Measured as bending capacity per kilogram, the two are equally efficient (35.8 against 35.9 cm³ per kg/m), so on a pure steel-tonnage basis there is nothing to choose between them. The decision comes down to availability, connection detailing and what the rest of the frame uses.
These come from different catalogues, so treat the swap as a design change rather than a like-for-like substitution. UB sections are specified to BS EN 10365:2017 and W to AISC Shapes Database v16.0; the steel grades, tolerances and available lengths differ, connection details and bolt gauges are set out differently, and the two are rarely both stocked in the same market. Check availability before changing a section on a drawing to save a marginal amount of weight.
In short, these two are genuine equivalents. Pick whichever your supplier stocks and the rest of the frame already uses.