Estimate how much a pile settles under its working load. Enter the borehole log with a modulus for each layer - or let the tool suggest one from SPT N and cu - and it solves the Randolph and Wroth compressible-pile solution layer by layer, showing how the load is shed down the shaft and how much reaches the base. The same pile is also checked by TCVN 10304 clause 7.4.2, and a rectangular pile group by clause 7.4.3, against the settlement you allow. Free, in your browser, no login.
Free online calculator with step-by-step working and one-click Excel (.xlsx) and PDF export.
This free pile settlement calculator estimates how far a single pile settles under its working load, and how much more a pile settles when it sits in a group. It is the serviceability partner of the pile bearing capacity calculator: a pile can have ample capacity and still settle too much, and both EN 1997-1 (7.6.4) and TCVN 10304 (7.4) ask for the check.
Two methods run side by side so you can compare them: the Randolph and Wroth closed-form solution for a compressible pile, solved layer by layer through your borehole log, and the TCVN 10304 clause 7.4.2 formula. A rectangular pile group is assessed with the interaction factors of TCVN 10304 clause 7.4.3.
The head settlement is what the structure feels; the base settlement is smaller by the elastic shortening of the pile itself. The difference is large for long, slender piles, which is why a stiff pile material matters as much as stiff soil.
The calculator plots the axial load from the head to the tip. At working load most of it is shed into the soil by shaft friction, and in a long friction pile very little reaches the base - the figure makes that visible layer by layer, which is the information a load test with strain gauges would give you.
Piles in a group settle more than a single pile at the same load, because each pile sits in the settlement bowl of its neighbours. TCVN 10304 clause 7.4.3 adds an interaction term for every other pile closer than a limiting distance; the centre piles settle most and the group settlement is the mean.
Few site investigations measure soil stiffness directly, so the tool suggests one from what a borehole log does give you. N is first corrected to N60 for the hammer energy ratio. Published correlations scatter widely, so every suggested value is marked, its source named in the Details tab, and any layer can be given its own E from a pressuremeter, dilatometer or back-analysed load test.
The capacity tool's default pile: a 350 mm square precast pile, 24 m long with its head 1.5 m below ground, through soft clay into medium dense sand, carrying a service load of 650 kN. The moduli are left to the suggestions.
The two single-pile methods agree within 4% here. The group settles three times as much as the single pile at the same load per pile - the usual reason a group, not a single pile, governs the serviceability check.